Ref.No: | 62422000 |
Start date: | 15.12.2023 |
End date: | 14.03.2025 |
Approval date: | 15.12.2023 |
Department: | MINING AND METALLURGICAL ENGINEERING |
Sector: | MINING ENGINEERING |
Financier: | IMERYS BWKSITES ELLADOS ANWNYMH ETAIRIA |
Budget: | 62.000,00 € |
Public key: | 9ΥΥΕ46ΨΖΣ4-ΓΘ9 |
Scientific Responsible: | Prof. BENARDOS |
Email: | abenardos@metal.ntua.gr |
Description: | THE PROJECT ENCOMPASSES THE GEOLOGICAL AND GEOTECHNICAL CONDITIONS OF THE UNDERGROUND ACCESS WORKS AT THE KAMARA 2 MINE, AND MORE SPECIFICALLY, THE MAIN ADITS S617, S592, S617-1, S1, S2 AS WELL AS THE CONNECTING DRIFT S617-S592 BETWEEN THEM. AT THE SAME TIME, THE NECESSARY PROTECTION / SUPPORT MEASURES WILL BE PROPOSED FOR IMMEDIATE IMPLEMENTATION IN ORDER TO CONTROL / MITIGATE ANY RISK CONDITIONS THAT MIGHT EXIST AND THUS ACHIEVE THE STABILITY OF THE UNDERGROUND OPENINGS AND THE SAFETY OF THE UNDERGROUND EXPLOITATION. |